Preliminary detention storage volume from peak inflow, allowable outflow, and storm duration using the simplified triangular hydrograph method.

Drainage & Hydrology · Modified Rational Method

Detention Pond Sizing

This calculator estimates the storage volume a detention pond needs to reduce post-development peak runoff down to an allowable release rate, using the simplified triangular hydrograph approach common for preliminary sizing on small to medium sites. It pairs naturally with this site's Rational Method and Time of Concentration calculators, which supply the peak inflow and storm duration inputs.

The method assumes the inflow hydrograph rises and falls linearly over the storm duration while the outflow structure releases at a constant allowable rate. The required storage volume is the excess between the two, integrated over the storm — a quick, conservative first estimate before full hydrograph routing.

Simplified Triangular Hydrograph Method
V_req = 0.5 · (Q_i − Q_o) · t_d · 60 [ft³, cfs, minutes]
Reference: Modified Rational Method, simplified triangular-hydrograph storage sizing — standard preliminary approach for drainage areas under roughly 20 acres per common municipal stormwater manuals. Verify against local jurisdiction requirements.
Worked Example

A site with a post-development peak inflow of 12 cfs must release no more than the 4 cfs pre-development peak, over a 20-minute critical storm duration. The required storage is V_req = 0.5 × (12 − 4) × 20 × 60 = 4,800 ft³, or about 0.110 acre-feet — a 67% reduction in peak flow that the pond's storage and outlet structure must be sized to achieve.

Read the Full Guide →

Detention Pond Sizing Calculator

Simplified triangular hydrograph · imperial units

Post-development peak — from the Rational Method calculator
Typically the pre-development peak rate
Often approximated near the time of concentration
Detention Pond Sizing Results
Required Storage Volume
Required Storage (acre-ft)
Net Flow Reduction
Peak Reduction
This is a preliminary estimate only. Final pond design requires full stage-storage-discharge routing (e.g., SCS/TR-55 unit hydrograph) against the actual pond geometry and outlet structure. Requires PE review.